Relativity Space@relativityspace·Nov 13

🔥 Hot metal. Blue fire. Stage 2 completed its mission duty cycle on the first try: a 400+ second burn and coast demo including an igniter hot fire, demonstrating everything it needs to do in flight.

7:17
Relativity Space avatar
Relativity Space@relativityspace·Nov 16

October was a full month of progress for Terran R. 🚀 The historic A2 test stand – built for Apollo and later used for Space Shuttle engine testing – is back in action, now firing for Terran R. Plus: ✅ Interstage structural testing complete ✅ Thrust structure breakover + mate with stage one in progress ✅ LC-16 lightning protection towers at full height ✅ Propellant tanks cryo-shocked

3:38
Relativity Space avatar
Relativity Space@relativityspace·Oct 16

🔥 Just another day at Stennis. Stage 2 successfully completed its first integrated hotfire! The A2 test stand was originally built in the 60s to support Saturn V Upper Stage testing (S-II). It was later reconfigured to be a single engine test stand for Shuttle Main Engine testing and development. The last Saturn V Stage test occurred October 30, 1970 on A2. It has been 55 years, 11 months, and 17 days since A2 supported stage testing capability. As of this morning, it is now 0 days.

0:25
Relativity Space avatar
Relativity Space@relativityspace·Oct 15

Building the infrastructure to launch Terran R. September brought several key milestones across LC-16's launch pad and ground systems. ✔️ The east lightning protection system tower reached its full height of 530 feet. ✔️ Structural steel on the east side of the launch table is complete. ✔️ Permanent 480-volt power infrastructure energized at the pad.

0:34
Relativity Space avatar
Relativity Space@relativityspace·Oct 14

September was a big month for test operations across our sites. 📍 NASA Stennis, MS Stage 2 completed its first wet dress rehearsal! The team put the stage through flight-like propellant loading, COPV fills, engine chill operations, and a simulated stage 1 ascent timeline, building toward its first integrated hot fire. 📍 Long Beach, CA All 13 Aeon R engines are installed on the thrust structure and are moving through integrated gimbal testing, validating their ability to pivot precisely to steer and stabilize the vehicle during flight.

1:26
Relativity Space avatar
Relativity Space@relativityspace·Oct 13

From tank integration to engine production, September builds kept the team busy. ✓ Installed the downcomer into the stage 1 flight tank ✓ All primary hardware on the stage 1 aft dome is complete, closing in on final integration ✓ Interstage drilling finished, now heading to the Tender Loving Crusher for structural testing ✓ First 2 ground station controllers stood up ✓ First welds complete for the Aeon V vacuum engine nozzle extension ✓ Flights 2 and 3 engines well into manufacturing with production ramping

1:06
Relativity Space avatar
Relativity Space@relativityspace·Oct 12

From the downcomer going into the stage 1 tank to stage 2 completing its wet dress rehearsal at Stennis, September brought progress across every discipline. 🔩 Build: The downcomer was installed into the stage 1 flight tank. The interstage completed drilling and was passed off to the Tender Loving Crusher ahead of structural testing. Engine production continues to ramp, with articles for flights 2 and 3 well into manufacturing. 🧪 Test: With all 13 engines installed, the thrust structure transitioned into integrated gimbal testing. At Stennis, stage 2 completed a wet dress rehearsal on the A2 stand, building towards the first hot fire test. 🏗️ Launch: The east lightning protection tower reached its full height of 530 feet, the east launch table structural steel is complete, and permanent 480-volt power has been energized at the pad.

3:22
Relativity Space avatar
Relativity Space@relativityspace·Sep 16

LC-16 is taking shape. ✔️ Flame diverter installation is underway, built to redirect the immense heat, exhaust, and acoustic energy generated at launch. ✔️ Launch table steel is going up alongside continued work on the LNG tank farm and lightning protection system, raising the first sections of the 531-foot towers. ✔️ Inside the HIF, outfitting continues as the transporter erector upper strongback takes shape. ✔️ The engineering support building is officially open, giving the teams who will operate Terran R launch campaigns a new home on-site.

0:49
Relativity Space avatar
Relativity Space@relativityspace·Sep 15

Hardware across the vehicle continues to advance through test. 📍 Long Beach, CA The first stage downcomer completed its full acceptance test campaign. This flight-critical component, which routes liquid oxygen from the tank to the engines, is now cleared for integration. 📍 NASA Stennis, MS Stage 2 is back in the hangar after completing cryoproof and COPV proof testing. Post-test inspections are underway ahead of Aeon V installation. A2 is being prepped for hot fire, with LOX farm flushes and heat exchanger activations. On the R stand, acceptance testing of flight 2 Aeon R engines is underway.

0:56